You need a commencement notice if you are:
- Constructing a building
- Making a Material alteration to a building
- Extending a building
- Materially changing the use of a building
- Carrying out any works in connection with the material alteration of a shop, office or industrial building
The Building Control Authority must be notified between 14 and 28 days before you start construction on site, and it must be accompanied by the correct fee. The current fee for a commencement notice is €30 per building
Apply for a Commencement Notice
To apply for a Commencement Notice each party (owner, designer, builder and assigned certifier) to the notice must first register with the Building Control Management System (BCMS).
The Building Control (Amendment) Regulations SI 9 of 2014 recommends that the BCMS site hosted at www.localgov.ie is used as the preferred means of building control administration.